Welcome back
Here is the current status of your project.
Current phase
Building permit
Preparing and submitting the permit application
Phase progress 65%
Last update: 20 April 2024
View details What happens next?
This week
What happened
- • Public inquiry has started
- • All advisory bodies have been requested by the municipality
What we are waiting for
- • Waiting on fire brigade advice (expected within 2 weeks)
What we need from you
- • Confirmation of your budget for the tendering
Action required
1 request from your architect
Your project team
MJ
Marie Janssen
Lead architect
TD
Thomas De Smet
Assistant
Recent activity
Milestone "Indiening Omgevingsvergunning" afgerond
1 April 2024
Document "Ingediend Dossier" toegevoegd
1 April 2024
Openbaar onderzoek gestart - wachten op gemeente
5 April 2024
Nieuw bericht van Marie Janssen
10 April 2024